Locaters Pty Ltd were engaged to provide locating, surveying and reporting of the existing subsurface utility network for the Early Works Clearance Zone package. This work was essential enabling work to prove the path of the proposed light rail corridor from Circular Quay to Randwick.
Our role was to collect and distribute subsurface utility information accurately and efficiently to the project management team including those from Laing O’Rourke , Transport for NSW and other consultants.
Project issues:
Congestion of underground networks within the CBD
High-risk networks including high pressure gas, optic fibre
High profile environment working around the public
Unidentified utilities
Short windows of opportunity
How we we helped:
Gained thorough understanding of client requirements
Supplied multiple staff, as needed, to accommodate project demands
Undertook utility identification and reporting
Delivered data in PDF and electronic formats
Interesting Facts About This Early Works Project (between October 2014 & June 2015):
Almost 1.3km of slot trenching surveyed
10,619 utility survey points measured
284 unidentified/unexpected and 487 expected pipes and/or cables were uncovered, surveyed and reported on
Locaters were nominated for a supply chain forum award by Laing O’Rourke recognising our contribution to their project.